Georgia PSC staff does not object to Georgia Power–OpenAI 3.2 GW contract

Georgia Power said staff did not object to the July-filed private contract for OpenAI’s Project Camellia in Effingham County, about 3,200 MW in phases 2028–2032. Under 2025 large-load rules (≥100 MW), a staff objection would have opened a 30-day commission review. OpenAI is to pay full infrastructure cost and commit up to 1,000 MW of demand response. Public contract summary expected early September. Company language says approved; contemporaneous reporting describes a staff non-objection, not a recorded vote of the five commissioners. Sen. Raphael Warnock on Aug 28 called for a statewide construction moratorium. That is not a bill or an order.

Why it matters

Largest single utility large-load step of the week, and a test of Georgia’s 2025 cost-shift rules.

Companies

Risks

Sources

This page is server-rendered for crawlers and readers without JavaScript. Site scripts enhance navigation and related desk features when available.